McIntosh Perry provided Temporary Structures Design of the scaffolding system design for work on the Burlington Skyway Bridge at the S1 & N1 pier locations. The scaffolding was used to access the existing bridge steel members to repair, sandblast and repaint. The scaffolding is approximately 200’ high.
When the bridge was damaged during a traffic incident in 2014, our Temporary Structures team was called in to assess the damage and provide recommendations for the course of repairs.
Ask us how we can help with your next project. Call toll free 1-888-348-8991.